In high post-monsoon pressure to strengthen road infrastructure across the gurrogram, municipal commissioner Pradeep Dahiya said he set a goal by the end of September to fulfill all potholes and complete the repair and strengthening of all roads by the end of October, the official said. This comes after heavy rains beaten by the city at the beginning of this month, which further causes the growth and traffic growth.
Representative of the Commissioner Ajay Kumar, who informed about the current state of ongoing road works during the audit meeting of videoconferencing, chaired by Chief Minister Nayab Saini, the same for the October term.
HARYANA CM ON THE GURRONGRAMY roads
Saini ordered officials to ensure that no negligence would be tolerated in the construction and repair of roads, including all departments that had to accomplish their tasks in the set timeline so that “citizens could get better road facilities”.
He stressed that anywhere the roads are damaged due to precipitation, repaired must be carried out immediately on the basis of a priority base, the official said.
“DC reported that to repair 29 roads with a total length of 23 kilometers below the PWD (B&R), the company estimate £17 crore was ready. After floating offers, work will begin in the next three weeks. In the area of HSVP sector-37 repair 46 roads (total length 5.25 km) for the price £3.25 Crore has already started and will be completed by October. Similarly in the Pataudi Estimation Estimation £9 CRORE was ready to repair 72 roads (total length of 13 km), ”said the clerk.
“DC further reported that the Haryan Agricultural Marketing Council has 110 roads, of which 2 roads in the Budhera area were damaged during the monsoon.
Dahiya mentioned that MCG identified 110 kilometers of roads that need repair, with estimated costs approximately £60 crore, said the clerk. At the meeting he also took part in the city commissioner Manesar Ayush Sinha and other relevant departments.