Traveling via Aroor-Thuravoor Stretch of National Highway (NH) 66 has become a test of commuters, with traffic mud and long delays now part of everyday life.
The ongoing construction of an elevated highway over the existing four -lane road has changed the corridor to the main narrow narrow west. Yet in the middle of chaos lies a flash of hope – the promise of smoother rides forward and insight into Keral’s developing infrastructure.
The construction of 12.75 km of six -abrasive highway, part of the expanding project NH 66, makes progress with 65% of completed work. Project 2 200 Crore, as soon as it is completed, will be the longest overpass in the country under the National Motorway Office of India (Nhai).
“All 360 pillars and 3,000 beams were built. Girder is currently underway. It is working on three east ramps and a toll square has also begun. The whole project is expected to be completed until May 2026,” Nhai said.
The work on the project began in 2023. The day and night are deployed approximately 2,500 workers and 350 machines to take place. However, the building is not without its challenges. Traffic constipation, sometimes lasting hours, became a routine.
Loss of life
According to Aroor-Thuravoor Janakeeya Samithi, at least 28 people have lost their lives in road accidents from the beginning of increased highway work. Several workers involved in the construction also died.
“The raised highway is very needed. Most accidents were the result of ruthless driving. The vehicles should strictly follow the rule with one stripe. It will help to some extent reduce chaos. Samithi.
In order to alleviate overload, Nhai sanctioned means to strengthen two parallel roads-Thuravoor-Kumbalangi and Thuravoor-Makekkadavu-like alternative routes. Meanwhile, Nhai officials said that the construction of an elevated motorway was stopped in several places due to the delays of the State Electrical Council of Kerala when moving extra power lines and energy underground cables.
Published – 6 June 2025 20:45