TAPI Pipeline Reaches Afghanistan: What is the $10 billion project and can gas from Central Asia reach India via Pakistan? | Today’s news

The Turkmenistan-Afghanistan-Pakistan-India (TAPI) gas pipeline, envisioned as a major energy corridor connecting Central Asia with South Asia, has taken another step forward, with construction of its Afghan section progressing towards the city of Herat.

Turkmenistan expects to complete the last part of the pipeline connecting its border town of Serhetabat with Herat by the end of 2026.

The section is expected to start delivering gas to Afghanistan in early 2027, which could give new impetus to a project that has been stalled for years due to geopolitical tensions, security concerns and financial difficulties.

This development is significant for India, which is among the proposed beneficiaries of the ambitious gas pipeline.

If completed, TAPI could allow India to access Turkmenistan’s vast natural gas reserves via Afghanistan and Pakistan, opening up an alternative energy corridor to meet its growing demand for natural gas.

The section approaching Herat is only a small part of the proposed 1,800km pipeline, with more challenging sections through Afghanistan and Pakistan yet to be completed.

What is the TAPI pipeline project?

The TAPI pipeline is a proposed 1,814 km natural gas transportation project connecting Turkmenistan to Afghanistan, Pakistan and India.

It is intended to transport gas from Turkmenistan’s Galkynysh gas field, one of the largest in the world, to energy markets in South Asia.

With a planned annual shipping capacity of 33 billion cubic meters (bcm), the project is estimated to cost around US$10 billion.

The pipeline will start at the Galkynysh gas field in Turkmenistan before crossing Afghanistan and Pakistan to reach Fazilka in Punjab, near India’s border with Pakistan.

Its designed route is divided into three main sections:

– Turkmenistan: An approximately 214 km pipeline will connect the Galkynysh gas field to the Afghan border.

– Afghanistan: Approximately 774 km will pass through western and southern Afghanistan, including Herat and Kandahar.

– Pakistan: Approximately 826 km will pass through Quetta and Multan before reaching Fazilka in Punjab, India.

Under the proposed gas sharing agreement, India and Pakistan are expected to receive 42% of the transported gas, equivalent to around 14 billion cubic meters per year. Afghanistan is allocated the remaining 16%, or approximately 5 billion cubic meters, in addition to receiving transit fees from the pipeline.

TAPI Pipeline: What is the latest progress in Afghanistan?

Recent construction activity has brought the project closer to its first operational milestone, although the entire pipeline is far from complete.

Turkmenistan completed its domestic section of the pipeline in 2019. Construction of the Afghan section formally began in 2024, with work progressing towards Herat.

At the Turkmen Energy Forum in October 2026, Turkmenistan said that the construction of the Serhetabat-Herat section had reached the suburbs of Herat. The country expects this section to be completed by the end of 2026, with gas shipments to the Afghan city expected to begin in early 2027.

According to Reuters, Turkmen officials believe that getting this initial section up and running could help attract international lenders and investors for the larger project.

Read also | India is planning a second gas switch as energy security comes to the fore

Muhammetmyrat Amanov, head of the Turkmen state company responsible for the TAPI project, told Reuters that the Herat section would help generate timely revenue and boost confidence among potential lenders.

The roughly 150 km Serhetabat-Herat section is estimated to cost $600 million, according to Afghan media. Its planned capacity is much smaller than the eventual 33 bcm3 annual capacity of the complete TAPI pipeline.

The initial gas deliveries are expected to support Afghanistan’s domestic needs. Plans identified by Turkmenistan include connecting a gas pipeline to the Herat Industrial Park, establishing gas distribution stations and developing a compressed natural gas complex. A private investor also proposed a gas-fired power plant near Herat.

This could provide an immediate economic incentive for Afghanistan to support the project, even before the pipeline is further extended to Pakistan and India.

Turkmenistan has some of the world’s largest natural gas reserves, making it an important potential supplier to energy-hungry economies across Asia.

The Central Asian country is estimated to hold around 5.3% of the world’s natural gas reserves, ranking fifth globally behind Russia, Iran, Qatar and the United States.

It could also deepen India’s economic engagement in Afghanistan and Central Asia and strengthen regional connectivity through energy infrastructure.

Can Central Asian gas reach India via Pakistan?

Despite recent construction progress, the possibility of Turkmen gas reaching India via Pakistan remains uncertain.

The biggest challenge is the political geography of the pipeline. TAPI has to pass through Afghanistan and Pakistan before reaching India, so its successful completion depends on the cooperation of all four countries involved.

The Taliban’s return to power in Afghanistan in 2021 has raised questions about security, political recognition and the availability of international funding for infrastructure projects in the country.

Although the Taliban administration has shown interest in the pipeline, security risks and uncertainty about the long-term political environment remain concerns for international investors.

Pakistan presents another big challenge. India and Pakistan have historically had strained relations, with diplomatic tensions rising after the Pahalgam terror attack and security concerns often affecting bilateral cooperation.

Another hurdle is funding. With an estimated project cost of US$10 billion, TAPI requires significant investment and long-term commitments from participating countries and international lenders.