KERC mandates 43.33% renewable energy for Escoms industries by 2030
Apart from Escoms, KERC has appointed mandatory entities including open access consumers with contracted consumption of 1MW and above who use electricity through open access. | Photo credit: IMAGE FOR REPRESENTATIVE PURPOSES ONLY
The Karnataka Electricity Regulatory Commission (KERC), through its proposals for the Renewable Energy Regulations 2026, has suggested that Escoms and large electricity consumers such as industries and commercial enterprises in the state should increasingly use renewable sources such as solar, wind, hydropower and biomass instead of relying on conventional sources such as coal.
As part of this proposal, it also proposed renewable resource obligation (RPO) targets for various entities. While the target was only 35.95% in 2026-27, the commission has set the target at 43.33% in 2029-30 by increasing it in small increments every financial year. For example, in 2027-28 the target has been raised to 38.81% and in 2028-29 it will be 41.36%.
In addition to Escoms, the commission has named mandatory entities including open access consumers with contracted consumption of 1MW and above who purchase electricity through open access. This includes industrial, commercial or large institutional entities that generate electricity primarily for their own consumption.
Drought increases dependence on coal
Due to this year’s poor monsoon and shortage of hydro and wind power, dependence on coal supplies has increased. Recently, Karnataka Power Corporation Limited (KPCL) clarified that daily coal supply to Ballari Thermal Power Station (BTPS) from Baranj coal mines will be increased from 16,000 tonnes per day (TPD) to 25,000 TPD.
Similarly, Raichur Thermal Power Station (RTPS) will also receive 4,000 TPD. KPCL has set a daily production target of around 100 million units (MU) this year, which will require 20 rakes of coal per day.
Higher RPO targets across India
“Not just KERC, these higher targets for RPOs have been proposed across the country. The Union Ministry of New and Renewable Energy has suggested extending RPOs to various stakeholders. Hence, we have modified the RPO targets and added them to the new draft regulations,” said KERC Chairman P. Ravikumar.
Apart from wind and hydropower, KERC also specified distributed renewable energy, which is electricity generated from smaller solar projects below 10MW, rooftop solar installations and so on. It also specified resources such as biomass and energy from municipal solid waste.
One important provision in the KERC proposal is that wind and hydropower RPOs must be met through projects awarded after March 31, 2024. This means that the regulation differentiates between newer renewable energy projects and older ones.
What if RPO targets are not met?
If industries cannot meet RPO targets, the proposal gives obliged entities three ways to meet their renewable energy commitments, including purchasing electricity produced through solar, wind, hydro or other renewable sources, or from traders and on the open market.
Another way is to buy Renewable Energy Certificates (RECs); RECs generated from the entity’s own renewable energy projects or acquired through virtual power purchase agreements are also eligible. Redemption of RECs to meet the RPO must be governed by Central Electricity Regulatory Commission regulations. If the RPO is not met through renewable energy or RECs, the entity can pay a feed-in price determined by the CERC, the proposal said.
RPO monitoring
According to the proposal, all entities must submit details of electricity consumption and renewable energy consumption by July 31, 2027. This will be monitored by the state agency, which will also submit a compliance report by August 31, 2027. In case of non-compliance, KERC can initiate proceedings under Section 142 of the Electricity Act, 2003, the proposal says.
Published – 22 Nov 2026 19:47 IST