Telangana High Court, who observed that the courts could not be spectators for violations, such as building other floors from the original plans, refused to provide power connection to the Hyderabad building without the owner of the cast.
The justice of Nagesh Bheemapak of HC, which is in writing to seek the TGSPDCL authorities in writing to provide the power supply plus the five -corner building in Himayathnagar, ordered the petitioner to first secure before GHMC. Only after the production of the occupancy certificate should the supply of energy be published in this building, the judge said in the order.
The petitioner Mohammed Arif Riswan’s advisor claimed that in several cases the HC ordered the authorities to provide power connections if the builders provided the obligation to submit a certificate of occupation later. The judge noted that several buildings of buildings give a approved plan and increase other floors.
Later they applied for a system of building regularization to legalize deviations, while the civic body was unable to take any steps. The judge quoted a case -law law in which the Supreme Court stated that services such as electricity, drinking water and sewerage systems will only be provided when submitting the occupancy certificate.
Published – 16 August 2025 21:38