BMLTA Addendum Announced: Tunnel Roads, Elevated Corridors to Avoid Institutional Scrutiny

The latest amendment to the Act on BMLTA concerns § 19 paragraph 5. | Photo credit: K. MURALI KUMAR

Amid public criticism, the Karnataka government recently announced the Bengaluru Metropolitan Land Transport Authority (Amendment) Act, 2026 (BMLTA), which will shield several controversial infrastructure projects planned between 2022 and mid-2026 from institutional scrutiny.

After the Act was passed in 2022, the BMLTA was finally made operational in mid-2026 with the notification of its rules. The latest amendment to the BMLTA Act refers to § 19 paragraph 5.

The provision of the section retroactively validates decisions and actions in respect of projects initiated between the passing of the BMLTA Act in 2022 and the notification of the 2026 Rules, deemed to have been carried out under the Act.

These decisions and actions include “decisions taken, plans prepared, operations carried out and proceedings in progress”, thereby providing retrospective legal protection to urban transport projects in Bengaluru.

It went by in a hurry

The Congress government introduced the controversial BMLTA (Amendment) Bill, 2026 during the monsoon session held in August. The bill was passed in both houses without any meaningful debate amid high drama as Bharatiya Janata Party (BJP) leaders protested and demanded the resignation of former minister B. Nagendra, who is accused of fraud.

An official document reviewed by The Hindu said the bill received the assent of the then Governor of Karnataka Thaawarchand Gehlot on October 9. The amendment was subsequently announced through the State Gazette.

The amendment will put the projects being pushed by Chief Minister DK Shivakumar, including tunnel roads, Sancharayukta, 11 elevated corridors and the Hebbal short tunnel, out of the purview of BMLTA, the city’s transport planning authority.

Civic activists condemned the amendment when it was passed during the session. They emphasized that their intention was to protect controversial projects by allowing them to escape scrutiny under BMLTA rules, against which several public interest litigations (PILs) have been filed.

Rule to section

The latest amendment essentially incorporates the substance of Clause 24, the Savings Clause of the BMLTA Rules. According to an RTI response from the Urban Development Department (UDD) reviewed by The Hindu, the rules received more than 200 objections, mostly Rule 24, after the draft rules were published in July this year.

Several citizen groups called the provision “unconstitutional” and “unscientific” in their objection. The objections highlighted that this single savings clause would exempt “distressed projects worth more than ₹1,00,000 crore” from the purview of the BMLTA.

One of the objections pointed out that the savings clause would defeat the very purpose of establishing the office. Meanwhile, motions submitted by citizens urged the UDD to scrap Rule 24 to ensure accountability and transparency.

However, the UDD went ahead and announced the rules without deleting the savings clause. As a result, several PILs challenging the rule have been filed and hearings are underway.

Pointing to the large number of objections and the alleged absence of any changes in the rule, environmental activist Dattatraya Devare said raising public objections was merely a formality.

“The authorities barely care about public opinion, which raises questions about the importance of public participation,” he told The Hindu.

Now, while the PILs are still being heard in court, the government has incorporated the earlier provision, which existed only as a ‘rule’, into the Act itself through an amendment, over objections from citizens. It remains unclear what will happen to the savings clause and the pending legal challenges now that the provision has been incorporated into part of the bill.

Published – 15 Nov 2026 21:34 IST