Chief Secretary K. Vijayanand directed the AP Central Power Distribution Company Limited (APCPDCL) and district officials to ensure timely completion of all ongoing power projects, with special focus on rooftop solar panels, feeder-level solar systems, enhanced distribution sector scheme (RDSS), smart metering and EV charging infrastructure.
He also highlighted the need for faster finalization of land required by solar projects, speedy conclusion of power purchase agreements and improved system reliability and consumer service standards.
In a review meeting with District Collectors A. Thame Ansaria (Guntur), DK Balaji (Krishna) and G. Lakshmisha (NTR District), AP-Transco Joint MD G. Surya Sai Praveen Chand and CPDCL CMD P. Pulla Reddy about other senior officials at Vidyut Soudha who were taken against those responsible on Saturday and warned Mr. Vijaan that any intention for any action would be taken here on Saturday. delays in the implementation of the above-mentioned projects.
Solar panel projects of more than 190 MW covering more than 76,000 farm pumps have been awarded in several districts at a competitive rate of ₹ 3.09 per unit, he noted and directed officials to complete finalization of land within the stipulated time frame, execute PPAs without delay and ensure strict adherence to project schedules.
On RDSS, Mr. Vijayanand directed that the contractors complete all loss reduction works by March 2026. Officials told him that 100% feeder metering has been completed and work on smart metering and infrastructure is progressing steadily across consumer categories.
The CS also reviewed the PM E-Drive Scheme, under which it was planned to create infrastructure for charging electric cars in more than 90 locations. The meeting was attended by NREDCAP VC and MD M. Kamalakar Babu, CPDCL Directors TVSN Murthy and A. Murali Krishna Yadav and others.
Published – 20 Dec 2025 20:25 IST