After being tired for almost 16 years, the Tumacuro railway line is finally witnessed by rapid progress, with more than 96% of the desired land is now handed over to railways and civic works in all key segments.
In an interview with Hindu, Deputy Commissioner Tumacura Subha Kalyan said: “In the last 12 months we have been able to systematically remove most of the narrow places that stopped this project for more than ten years.
The 206 km railway line, which connects tutukuru in Karnataka with Rayadush, passes and five majority sections-trutch-kukere, Urukere-Korupce, corrupt, Madhugiri, Madhugri-Madakasira and Madakasirali. According to land that is now available in all five parts, civilian officials have launched civilian work in the hallway.
Mrs. Kalyan said the administration completed the handover of 331 acres and 16 gunta soil, processed 110 acres to obtain and completed joint measurements for another 108 acres. In addition, 19 hectares were filed under the acquisition through preliminary notifications and all required approval notifications were accelerated.
“Many delays were caused by unresolved disputes and outdated income records. We organized Taluk-Who Resolution camps to help recipients update their land records and accept compensation without delay. In the area, and in terms of officials and regulate the land, and are regulated and regulated in the officials, and in the area, and regulate, and in the area where they are devoted and ensuring smooth soil, which has been in the dispute for years, also solved payments, ”she explained.
The Tumacuru – Rayadurga project is carried out at estimated costs of 2,500 GBP Crore and the railway line will reduce the distance between Tumacura and Ballari by 130 km, which significantly increases the railway connectivity to the Kalyana Karnataka area.
Senior Southwest Railway Clerk said these projects play a key role in increasing Tumacura’s connectivity with other parts of Karnataka. “After completion, the railway line is expected to significantly increase the connectivity and economic development in regions such as Madhugiri and Pavagada. The main obstacles to the acquisition of land is now expected that the Tumacura railway – Rayadurga will be planned for 2027,” added SWR official.
Published – 14 June 2025 9:32